ELCID Test

ELCID test on Generator 400 MW

ELCID test on Generator 400 MW
ELCID test on Generator 400 MW...
Our EL CID facility is provided with 4 excitation cables, normally used for Hydro Generators, for the large turbo generators is require very long excitation cables, 40 meters or more depending of the stator length. For this unit we used 3 extension excitation cables to supply the excitation in the stator bore.
EL CID test on 3x65 MW Hydro Generators, 288 slots.
EL CID test on 3x65 MW Hydro Generators, 288 slots. (1)

Generators to be assembled at site, the stator core was stacked with overlapping method and  there is NO splitting core inside.

 

Core stacking process assembly

Core stacking process assembly
Core stacking process assembly
Core stacking process assembly (2)

Stator core are clamping by compression bolts and providing with the insulation tube at top and bottom side

Core stacking process assembly (3)
Core stacking process assembly (4)
Core stacking process assembly (5)

TESTING

During the ELCID test we identify high fault current at several slot and distributed from the bottom core to top, the fault currents is much higher than other slot. Following are the screenshot of the ELCID single trace intersection.

TESTING
Single Trace Intersection Slot 87.
Single Trace Intersection Slot 87.
Single Trace Intersection Slot 88
Single Trace Intersection Slot 88
Single Trace Intersection Slot 89
Single Trace Intersection Slot 89
Combined slot 87 and 89
Combined slot 87 and 89

Single Trace with Combine slots were shown that the peak current are identified at both slot from the beginning to end core (from bottom to top).

Tracing the problems.

Inspection to be done at that slots, there are NO physical damaged or abnormalities were found, a Mega-ohm meter was used to measure the insulation of the compression bolts, that identified “zero” ohm.

Repair action.

The compression bolts to be removed from the core clamping and found rust on the bolts, we  suspect that the rust is cause the problems..

VOLTATERA.COM
VOLTATERA.COM

To improve the bolts, we try to cleaning and adding 0.1mm thickness of KAPTON® insulation and tapping onto the bolts, and then reinstalled and re testing with a Mega-Ohm meter and ELCID.

VOLTATERA.COM

After reinstall we measure the Insulation Resistance at 500 VDC, and the value was improved from 0 M-Ohm up to round 500 – 600’s Mega Ohm.

VOLTATERA.COM

Re Testing with ELCID

After all bolts finished repair, re test with ELCID performing on that slots, and the maximum peak current is 17mA

Re Testing with ELCID

Conclusion:

  • The rusting on the compression bolts is causing stator interlamination short.

Tubing insulation for the compression bolts is too short, it is not sufficient to cover contact free between compression bolts and the core

ELCID TEST ON THE HYDRO GENERATOR 35 MW WITH SPLIT CORE

 

The units are constructing with two splitting core. with splitting gap round 1.5mm, the manufacturer tolerance is 2.0mm, located at slot 61 and 181.

ELCID TEST ON THE HYDRO GENERATOR 35 MW WITH SPLIT CORE
ELCID TEST ON THE HYDRO GENERATOR 35 MW WITH SPLIT CORE

EL CID test.

During ELCID test high peak current occurred at the splitter areas, following is the screenshot the single trace intersection at slot 61, the peak current is 161 up to 270mA (from the bottom to the top side), with the max peak current 270mA with distance 0.694m from the bottom (turbine side).

EL CID test.

Single Trace Intersection Slot 181, the peak current is 135 up to 262mA (from the bottom to the top side), with the max peak current 262mA with distance 0.669m from the bottom (turbine side).

EL CID test.

 

Single Trace Intersection at non Splitter area

Single Trace Intersection at non Splitter area

The split core is potential to causing hotspot, to remove the hotspot at this area is need better cooling system than others.

VOLTATERA.COM (4)

Leave a Reply

Your email address will not be published. Required fields are marked *

Copyright © 2026 PT. Volta Terawindo Bhuwana | Power Generation Services